15 Tractor Augers, 4 JCBs, 8 tractors with assets, 10 Ajex transit mixers, 3 Hydra cranes, 4 Farana cranes, 10 forklifts, 4 truck-trailers, 3 pick-ups and 80 power-tool sets — around 60+ heavy machines in total.
Over 180 deployed personnel — 160+ skilled and semi-skilled workers, supervised by 4 site supervisors, 2 Civil Engineers and 1 Electrical Engineer.
Because the fleet and crew are company-owned rather than hired, we typically mobilise a working front within 7–10 days of a confirmed order, subject to site access and material availability.
Commercial
Yes. GSTIN 08BOPPK6277R3ZO, PAN BOPPK6277R. We are also a registered Adani group vendor under Vendor Code 0000198717.
Our executed projects are in Rajasthan (Jaisalmer, Bikaner, Fatehgarh) and Gujarat (Kutch, Khavda). We take on work pan-India where the scope and duration justify mobilisation.
Use the Get a Quote form with your project type, capacity in MW, location and timeline — or call +91 83020 52523 directly. We normally respond to a complete tender enquiry within one working day.
General
GCC is a civil, electrical and solar EPC contractor based in Bikaner, Rajasthan. Our core scopes are piling and pile foundation, MMS foundation, solar module installation, tracker erection, DC–AC electrical works, SCADA and weather monitoring, grading, road work, fencing and material supply.
Over 2000 MW across Rajasthan and Gujarat, including the 2000 MW Khavda Renewable Energy Park, 450 MW SBE Fatehgarh, 315 MW and 300 MW NTPC AC Block III, 296 MW NTPC Fatehgarh, 300 MW Keraliya and 200 MW SECI.
Adani Green Energy Six Ltd., Adani SLR ENR JMR One Pvt. Ltd., Adani Hybrid Energy Jaisalmer Three Ltd., Mahindra Susten Pvt. Ltd. and Sterling & Wilson Renewable Energy Ltd.
Have a solar project? Let's talk.
Send the capacity, the location and the timeline. A complete tender enquiry is normally answered within one working day.